Dordi Khola Project (27 MW) Progress Report

01-Project Progress Report-December,2013

The progress regarding the Project activities in the month of December, 2013 seems to be moderate. Renting of houses in Besisahar and Ramchowk phant for the establishment of site office and staff quarter has been done to facilitate for the field works in Lamjung and communication and negotiation in land acquisition with the local people. These houses will be rented till the completion of project’s own camps, office, staff quarters and gu... Read More »

Download

02-Project Progress Report -January,2014

In the month of January basically the progress is focused in land acquisition and tender design review. Kitta kat of land along the water conductor pipe with the help of staffs from Napi Bhibhag in the presence of local land owners is continuing. For the first 700 m stretch after the desilting basin, Kitta kat is completed and the negotiation with the land owners is going on.

According to the BOQ of civil works provided by Entura Hy... Read More »

Download

03-Project Progress Report-Feb,2014

The month February passed in negotiating with the land owners. However, as scheduled in the previous month we have been succeeded to purchase land for link road to headworks and land around the inundation area on the left bank of river. Field work for Kitta kat of the necessary land along the water conductor alignment with the help of staffs from Napi Bhibhag in presence of land owners has been completed but still negotiation in the rate is go... Read More »

Download

04-Project Progress Report-March,2014

About 9 ropani of land at the headworks area and pipe alignment has been purchased recently (10 kittas). A single package for service road, bridge construction at the headworks and fencing of the purchased land has been made and tender has been awarded to Rasuwa Construction Company by bidding process. Rasuwa Construction Company has already mobilized to the site. The negotiation process and purchasing of land along the pipe alignment is still... Read More »

Download

05-Project Progress Report-April,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola Hydropower Project with equity sharing in 49:51 ratios.

Download

06-Project Progress Update-May,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola Hydropower Project with equity sharing in 49:51 ratios.

Download

07-Project ProgressUpdate- June ,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola Hydropower Project with equity sharing in 49:51 ratios.

Download

08-Project PRogress Report-July,2014Progress Report July 14

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

09-Progress Progress Update-August-2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

10-Progress Progress Update-September,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

11-Progress Progress Update-October,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

12-Project Progress Update-November,2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

12-Project Progress Update-December-2014

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

13-Progress Progress Update-January-2015

Detailed Design is being conducted by Entura Hydro Tasmania. Hydraulic Designs of the Components have been completed and Structural Design is going on.

Download

14-Progress Progress Update-February-2015

Dordi Khola Hydropower Project is a Run- of River type hydroeletric projet with generating capacity of 27 MW.

Download

15-Progress Progress Update-March-2015

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. to develop Dordi Khola HPP with equity sharing in 49:51 ratios.

Download

17-Progress Progress Update-May-2015

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. with equity sharing in 49:51 ratio.

Download

18-Progress Update-July-2015.

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal. HPPL is promoted by IME Group and later joined by NRN Investment Ltd. with equity sharing in 49:51 ratio.

Download

19-Project progress update-August,2015

Dordi Khola Hydropower Project is a Run-of -River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd.

Download

22-Project Progress Update-November 2015

Dordi Khola Hydropower project is a Run-of River type hydroelectric projet with generating capacity of 27 MW in lamjung. The project is being developed by Himalayan Power partner Ltd. (HPPL) Kathmandu, Nepal.

Download

23 Project Progress Update-Dec.2015

Dordi Khola Hydropower Project is a Run-of River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power partner Ltd. (HPPL) Kathmandu, Nepal

Download

Project Progress Update-Jan.2015

Dordi Khola Hydropower project is a Run of River type hydroeledtric project with generating capacity of 27 MW in Lamjung. The proect is being developed by himalayan power partner ltd. (HPPL) Kathmandu Nepal

Download

25-Project Progress update-February 2016

Dordi Khola Hydropower Project is a Run-of- River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

The  Whole project area lies in Chiti, Dhodeni and Bansar VDCs in Lamjung district in western Nepal. It is conneted from Kathmandu by 170 km all weather metallic roads.

Download

26 - Project progress update-March-2016

Dordi Khola Hydropower Project is a Run-of-River type hydroeletric project with generating capacity of 27 MW in Lamjung district. The project is being developed by Himalayan Power Partner Ltd (HPPL) Kathmandu, Nepal.

Download

27 - Project Progress Report-April-2016

Dordi Khola Hydropower Project is a Run-of-River project with an installed capacity of 27MW. The design discharge of the proposed scheme is 15.28 3/s with the rated head of 199.51 m.

Download

28-Project Progress Update-May 2016

Dori Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

29-Project Progress Update-June 2016

Dori Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

30 Dordi Khola HP-Project Progress update-July 2016

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27MW in Lamjung. The project is being developed by Hialayan Power partner ltd. (HPPL) Kathmandu, Nepal.

Download

31-Project Progress update-August 2016

Dori Khola Hydropower Project is a Run of River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

32-Dordi Khola HP-Project progress update-October-2016

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project  with generating apacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner ltd. (HPPL) Kathmandu, Nepal.

The Whole projet area lies in Chiti, Dhodeni and Bansar VDCs in Lamjung district in western Nepal. It is connected from Kathmandu by 170km all weather metallic roads.

Download

Dordi Khola Hydropower Project Monthly Progess Report November 2016

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

36-Project Progress Update-Jan-2017

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

Project Progress update-March-2017

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

Dordi Khola Hydropower Project

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

Project Progress Updates- April 2017

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

Project Progress Updates- May 2017

Dordi Khola Hydropower Project is a Run-of-River type hydroelectric project with generating capacity of 27 MW in Lamjung. The project is being developed by Himalayan Power Partner Ltd. (HPPL) Kathmandu, Nepal.

Download

Notice

View All

News & Events

View Archive

Watch Video

Dordhi Khola Jalabidhyut Aayojana 2015
Dordhi Khola Jalabidhyut Aayojana 2015
© 2011-2014 NRN Investment Limited. All Rights Reserved.