04-Project Progress Report-March,2014

About 9 ropani of land at the headworks area and pipe alignment has been purchased recently (10 kittas). A single package for service road, bridge construction at the headworks and fencing of the purchased land has been made and tender has been awarded to Rasuwa Construction Company by bidding process. Rasuwa Construction Company has already mobilized to the site. The negotiation process and purchasing of land along the pipe alignment is still going on. TOR has been sent to the consultants for the construction supervision proposal asking to submit by next weekend.