02-Project Progress Report -January,2014

In the month of January basically the progress is focused in land acquisition and tender design review. Kitta kat of land along the water conductor pipe with the help of staffs from Napi Bhibhag in the presence of local land owners is continuing. For the first 700 m stretch after the desilting basin, Kitta kat is completed and the negotiation with the land owners is going on.

According to the BOQ of civil works provided by Entura Hydro Tasmania, draft contract packages has been prepared and accordingly the expression of interest (EOI) will be invited from the reputed contractor for shortlisting.